JCPenney Warehouse Liquidation – New Jersey
1M+ square foot multi-phase liquidation including racking removal, asset recovery, scrap loadout, and site restoration.
Scope of Work
MIWEC Asset Recovery Inc. was contracted to liquidate a former JCPenney warehouse facility in New Jersey spanning over 1,000,000 square feet. The scope included asset identification and removal, high bay racking demolition, wire removal, scrap recycling, and final sweep-out of the building for turnover.
Crews worked under an aggressive timeline with limited utility access and strict fire safety protocols in place due to the size and occupancy history of the structure.
Challenges & Solutions
Challenge:
45’ tall racking systems requiring fire-watch demo and off-hour cutting.
✅ Solution:
Multiple lift crews with fire guards performed phased takedowns safely.
Challenge:
Extensive copper and wire systems embedded in walls and conduits.
✅ Solution:
Wire recovery crews used non-destructive extraction for resale value.
⚡ Challenge:
Limited interior power and compressed project deadline.
✅ Solution:
Powered lifts and LED lighting operated off generators and battery tools.