Scope of Work

MIWEC executed the full decommissioning and demolition of a 350,000 SF biomedical research and pharmaceutical manufacturing campus at 350 Knotter Drive, Cheshire, CT. Scope included complete takedown of over 200 laboratory workspaces, 300 office units, conference centers, and mechanical spaces.

The project involved universal waste disposal, asbestos abatement, and dual-stage epoxy floor bead blasting with polishing in critical zones. All removal work followed strict containment, regulatory handling, and safety documentation standards.

Alexion Pharma

Services Provided

  • Pharmaceutical Facility Decommissioning – Full takedown of labs, offices, and mechanical spaces under regulated protocols.
  • Environmental Controls & Abatement – Asbestos removal, universal waste processing, and EPA documentation.
  • Epoxy Floor Bead Blasting – Dual-stage stripping and polishing in cleanroom and lab corridors.
  • Secure Containment & Documentation – Material logs, manifests, and chain-of-custody handling.
  • Lease Restoration – Final surface prep and compliance for turnover readiness.

Alexion Pharma

Challenges & Solutions

⚠️ Challenge:
Highly regulated pharmaceutical infrastructure requiring documented handling.

✅ Solution:
Chain-of-custody tags were used to track sensitive material throughout the removal process.

⚡️ Challenge:
Lab-grade ductwork and containment tied into multiple building systems.

✅ Solution:
Isolation cuts and phased takedowns were performed to preserve adjacent infrastructure.

⏱️ Challenge:
Project required coordination while portions of the building remained occupied.

✅ Solution:
Night shift crews and localized HEPA containment zones minimized disruption.

Timeline & Execution

The project was completed in 4.5 weeks, including permitting, HAZMAT handling, and closeout. MIWEC provided certified disposal logs, abatement documentation, and regulatory compliance records to support reuse of the site.

Results & Value

  • Facility completely cleared and polished per redevelopment spec
  • All documentation delivered to client and state agencies
  • Zero violations or delays despite active regulatory environment
  • Site prepared for new tenant reactivation

Explore Similar Closures

Newsday HQ
Newspaper + chilled water demo for redevelopment.

Midwest Fulfillment
MHE & IT infrastructure removal during phased shutdown.

Rail Car Sites
Hazardous system dismantling and multi-site scrap recovery.

Stop & Shop DC
Cold storage and ammonia handling with phased demo.

Need Help with a Regulated Facility?

From lab zones to secure cleanrooms, MIWEC ensures full compliance and safe turnover.
Request a consultation today.

Firm’s Legal Name

MIWEC Asset Recovery Inc.

Contact Info

Phone: 631-873-4357
Fax: 631-425-7638
Email: Sales@MIWEC-USA.com
Info@MIWEC-USA.com

Office Address

273 Walt Whitman Rd, Ste 125
Huntington Station, NY 11746

Scroll to Top